LRT-1 Cavite Extension Restarts Work; Portion of Cavitex-Paranaque Bridge to Close Until May 22


LRT-1 private operator Light Rail Manila Corporation (LRMC) has resumed work on the 11.7-kilometer Cavite Extension Project after receiving the green light from the Inter-Agency Task Force (IATF) and Department of Transportation (DOTr) to carry on with select repair and infrastructure works while the Enhanced Community Quarantine (ECQ) is still in place.

The scheduled test pit works (bridge and pipe inspection) required for the construction along the CAVITEX – Paranaque bridge has started yesterday and will end May 22, 2020. As a result, there will be a temporary road closure of the innermost lane (northbound) along CAVITEX – Paranaque bridge to give way to the necessary activities in the area during the same period. This was previously announced and rescheduled due to the government’s implementation of Enhanced Community Quarantine program last March 17.

Design works, assembly works, and select tasks at the precast yard area are also ongoing for the Cavite Extension Project—which would see the LRT-1 line reach Bacoor, Cavite.

Preventive and corrective maintenance works, including the replacement of air-conditioning compressor units, are now in progress to ensure the public of better service when LRMC resumes operations of LRT-1.

Public transport operations have been suspended since March 17 in line with the government’s ECQ enforced in Luzon.

“Rest assured that we are taking every opportunity during this time to come back better for Filipino commuters. We are taking great efforts to make sure our workers remain safe and healthy by following the proper guidelines and precautions set by the government,” said LRMC Chief Operating Officer Enrico Benipayo.